    SRM Planned Migration Fail Back Reprotect Fails

    OMSAAY Lurker

      Hi Everyone, I have a SRM 8.1 infrastructure I have been testing the fail over and fail back from Site A to Site B, being Site B my recovery site.

      The problem is that sometimes the DRP using the Planned migration runs correct and some times it send me an error message when reprotecting from Site B to Site A: "Operation Failed, VR Synchronization failed for VRM group STMXPTHBD010. Synchronization monitoring has stopped. Please verify replication traffic connectivity between the source hosts anthem target...." I keep thinking that this may be a network problem but when monitoring the network during the DRP execution nothing seems incorrect. Any ideas?