Hi Team,
we want to add third vRealize Automation Appliance to dedicated it at the scheduled tasks.
For example when it's necessary to update all Business Group : Reservation, Entitlements, DAY2, etc.... This task call vRA REST API to make the job.
Sometimes when the scheduled task run the vRA REST API become done, doesn't respond and this impact our customers.
To doesn't impact the Production portal we want to add a third appliance as a not a member of load balancer.
If we change our scheduled tasks to use a specific REST API on the third appliance we think it's a good solution.
But just one question, when we have a third appliance it's mandatory to enable Synchronous Mode on PostgreSQL database ?
Thx for your feedback.