Hi everyone
On one of our environments, we have to go back to compression only due to performance recommendations :
We checked if everything was correct in terms of space, policies and health of each of the esxi but for some unknown reason, the conversion fails at 10% : General vSAN error. Resource check failed - Internal failure happened during the resource check. Please check clomd.log
On the host in question, we've checked the clomd.log (in attachments) and the only error I see is the multiple values like this : CLOMDecom_ComponentNeedsEvac: Could not find disk 00000000-0000-0000-0000-000000000000
But i'm not sure is this is the problem relative to the situation.