I understand that and I have recovery plan setup with the primary data node powering on first.  The problem is, the node that is primary can switch and I would never know it until I try to recover them at the DR site. Node 1 is primary right now and everything should work fine but, if node 2 becomes the primary down the road and we run the recovery plan, it's going to power on the wrong node first.

I guess the other option would be to somehow have the app send an alert that triggers a script to edit the recovery plan each time the nodes fail over but, that seems like a lot more work than just creating a snapshot in the unlikely event we ever have to recover these VMs during a disaster.