Hi all,
i am wondering if i have to build the whole NSX-T overlay network like TEP pools, Transport Zones, Edge VMs, N-VDS and so on to be able to use the Micro-segmentation option?
Thanks,
MahmoudZRaboe,
Overlay is not required, but the workload will need to be connected to a N-VDS. So, after NSX-T is installed (i.e. Mgmt. and Control Plane up, hosts added as Fabric Nodes, etc) you will...
-Create VLAN transport zone
-Add VLAN Transport Zone to the transport nodes
-Create VLAN based Logical Switch
-Move/create VM’s vnic to VLAN based Logical Switch created on N-VDS
-Create grouping and DFW policy on NSX-T
MahmoudZRaboe,
Overlay is not required, but the workload will need to be connected to a N-VDS. So, after NSX-T is installed (i.e. Mgmt. and Control Plane up, hosts added as Fabric Nodes, etc) you will...
-Create VLAN transport zone
-Add VLAN Transport Zone to the transport nodes
-Create VLAN based Logical Switch
-Move/create VM’s vnic to VLAN based Logical Switch created on N-VDS
-Create grouping and DFW policy on NSX-T
Thank you vLinge, i thought we had to do the overlay zone for micro-segmentation
Thanks,