Hello Guys

I would like your help to clarify the following

I have a Primary Site with VCF 4.5 with 4 nodes, and a second Site with VCF 4.5 with 4 nodes that are also not productive.

I have installed a Witness to configure a Stretched Cluster, but I need to know which is the best option.

1.- Carry out a decommissioning of the secondary site nodes and add them to the primary site.

2.- Reinstall the ESXi nodes and add them to the VCF of DC1 and then configure the Stretched Cluster.

I will appreciate your comments in this regard to find the best option to implement the solution.

Thanks


Sebastian

 

Labels (2)
Tags (1)
Reply
0 Kudos
2 Replies
shank89
Expert
Expert

I would decommission them and then too ensure they are clean rebuild them.

Once complete you can commission and stretch.

 

If you need some help with the process https://youtu.be/kpfobXvv1ZU

Shashank Mohan

VCIX-NV 2022 | VCP-DCV2019 | CCNP Specialist

https://lab2prod.com.au
LinkedIn https://www.linkedin.com/in/shankmohan/
Twitter @ShankMohan
Author of NSX-T Logical Routing: https://link.springer.com/book/10.1007/978-1-4842-7458-3
Reply
0 Kudos
DeviVmware
VMware Employee
VMware Employee

In VCF, the Recommendation is always to reinstall the OS when it is reused. 