Hi,
From the VMware KB: Operational Limits for SRM 5.1 and vSphere Replication 5.1 we found that there are some limitation from the SRM
Can anyone tell me, what is the meaning of "Concurrent Recoveries", maksimum 10 .
Is it count by VM (10 concurrent VM) or Recovery Plan (only 10 recovery Plan available)
Thanks
Hi,
Suppose if you have 15 recovery plan, then at time, simultaneously you can run 10 recovery plan, once this is complete, you can run rest of recovery plans.
Regards
Mohammed
Hi B4ndit,
It is concurrent recovery plans. I will update the KB to make this clearer.
Thanks!
Best regards,
Stuart
SRM documentation
Hi,
Suppose if you have 15 recovery plan, then at time, simultaneously you can run 10 recovery plan, once this is complete, you can run rest of recovery plans.
Regards
Mohammed
I have updated the KB to make this clearer.
Thanks!
stuart
thank you all
With SRM 4.x this limit was "soft", you could actually run more than 10 plans simultaneously.
Not sure it is the same with 5.x versions.
Michael.
>>With SRM 4.x this limit was "soft", you could actually run more than 10 plans simultaneously.
>>Not sure it is the same with 5.x versions.
I've run tests and DR test recoveries on 20+ plans concurrently using SRM 5.0 and 5.1 before with no issue although I dont recommend it if VMware dont advise going above 10, just saying its possible.
Thanks for the info.
Michael.