>1.Make sure Test/Dev VMs run on only Site 1 ESX servers and Prod VMs run on site 2 ESX servers
2 different clusters, that's all.
>2.Enable FT in case Site 2 goes down, all the prod VMs move to Site1 ESX servers after turning off the test/dev VMs.
If you're not gonna use SRM then scheduled replication can be done. For example with Veeam Backup & Replication.
>3.This process need to be automated.
It won't be fully automated process anyway. You have to press BIG RED BUTTON manually. But you can write a couple of scripts and automate failover process. Veeam Backup supports PowerShell scripting.
>4.Also want to take advantage of resourse pools.
Not a problem.
---
MCSA, MCTS, VCP, VMware vExpert '2009
http://blog.vadmin.ru
EMCCAe, HPE ASE, MCITP: SA+VA, VCP 3/4/5, VMware vExpert XO (14 stars)
VMUG Russia Leader
http://t.me/beerpanda