Does anyone know if there is any impact or something special I need to do when moving two host from a cluster into a new cluster. Due to our Oracle licensing we have to remove 2 host from the cluster and put them in a separate cluster. The host strictly has Development and Production Servers/Oracle DBs.
Thanks
You can disconnect and remove the servers from one cluster and add them to another cluster.
Hope you don't have any resource pools.
I do have resource pools in place but they are acting more as organizational containers than limiting resources. Each pool is set to unlimited. Will this still cause a problem?
So you are saying I can just disconnect the host and move it to the new cluster? Would I have to power down any of the current VMs within that host or can I leave them active?
It will not affect any machines but the hierarchy would change. Since you have plans of moving the hosts i think its not a problem.y