Hello Team,
I am running a Stretched Cluster with vSphere V6.7 and planned to upgrade to vSphere 8. So presently, the resource of both the Cluster host is under 50%. Customer is asking me to get everything upgraded and for the we are not given any downtime. I would like to know, whether is it possible to get this activity done without downtime or downtime is mandatory.
I was thinking about the plan to Migrate all the running VM in Host 1 to Host 2, and then upgrade vCenter, Management Host, and Cluster Host. Will there be any compatibility issue while migrating all the VM from host 1 having vSphere v6.7 to Host 2 with vSphere v8