I was taking a course which is as follows.

I have 2 resource pools which:

1st Resource Pool - Production 01

CPU Share - Custom 4000

CPU Reservation - 5234

CPU Limit - UNLIMITED

Memory Share - NORMAL

Memory Reservation - 3000

Memory Limit - UNLIMITED

•Expandable

Resource Pool 2 - Production 02

CPU Share - Custom 4500

CPU Reservation - 10139

CPU Limit - UNLIMITED

Memory Share - HIGH

Memory Reservation - 6000

Memory Limit - UNLIMITED

•Expandable

I need to create a new resource called PRODUCTION main pool where both resource pools and Production Production-1-2 would be created below this resource pool.

Witch metrics share, reservation and limit should I use?

Regards






*If you found this information useful, please consider awarding points for "Correct" or "Helpful"*

*Please, don't forget the awarding points for "helpful" and/or "correct" answers. *Por favor, não esqueça de atribuir os pontos se a resposta foi útil ou resolveu o problema.* Thank you/Obrigado
0 Kudos
1 Reply
MauroBonder
VMware Employee
VMware Employee

ok

*Please, don't forget the awarding points for "helpful" and/or "correct" answers. *Por favor, não esqueça de atribuir os pontos se a resposta foi útil ou resolveu o problema.* Thank you/Obrigado