I was taking a course which is as follows.
I have 2 resource pools which:
1st Resource Pool - Production 01
CPU Share - Custom 4000
CPU Reservation - 5234
CPU Limit - UNLIMITED
Memory Share - NORMAL
Memory Reservation - 3000
Memory Limit - UNLIMITED
•Expandable
Resource Pool 2 - Production 02
CPU Share - Custom 4500
CPU Reservation - 10139
CPU Limit - UNLIMITED
Memory Share - HIGH
Memory Reservation - 6000
Memory Limit - UNLIMITED
•Expandable
I need to create a new resource called PRODUCTION main pool where both resource pools and Production Production-1-2 would be created below this resource pool.
Witch metrics share, reservation and limit should I use?
Regards
*If you found this information useful, please consider awarding points for "Correct" or "Helpful"*
*Please, don't forget the awarding points for "helpful" and/or "correct" answers.
*Por favor, não esqueça de atribuir os pontos se a resposta foi útil ou resolveu o problema.*
Thank you/Obrigado