vCenter

 View Only
  • 1.  Converter Sync schedule?

    Posted Jun 12, 2013 12:36 PM

    Going over the advance options for syncronization i do not see any option for creating scheduled syncronizations?  Any ideas around how to accomplish this or are the syncronizations meant to be performed directly after an initila seed?  Should we not look to use this feature for continual syncs say days before a planned cut-over?   Also is there an enterprise version of the converter avilable for 5.0?

    thanks!              



  • 2.  RE: Converter Sync schedule?

    Posted Jun 12, 2013 01:49 PM

    Hello

    There is scheduled synchronization in Converter since 5.0. Here is a snapshot from 5.1:

    You should be aware that scheduled synchronization is available for Windows P2V to managed destinations only. Other restrictions apply to using synchronization (see p.71)

    You can schedule only one synchronization, though, no recurring scheduling.

    Converter as a vCenter Server plugin has been discontinued since 4.1 (if that is what you mean by enterprise version).

    HTH

    Plamen



  • 3.  RE: Converter Sync schedule?

    Posted Jun 12, 2013 02:04 PM

    Thanks for the response.  I have a 5.0 update 2 enviornment as the destination can i use the 5.1 converter or do i need to use the 5.0 converter?



  • 4.  RE: Converter Sync schedule?
    Best Answer

    Posted Jun 12, 2013 02:09 PM

    Converter 5.1 supports ESX and vCenter from 4.0 to 5.1