VDP schedule backup stop at 92%

We have a schedule backup to backup VM server every day. But until last week it was no response while backup at 92%. Then the backup job could not complete.

Actually, there was similar error before, but I created new schedule backup. Then problem could be fixed.

Does it related to VM server’s size or any setting? The server contains 2.22TB HD.

Could you provide any experiment? Thank you again!

Reply
0 Kudos
1 Reply
SavkoorSuhas
Expert
Expert

# mccli activity show --active

Is the job running?

If yes,

# mccli activity get-log --id=<obtained-from-above-command> | less

What point is it stuck at? <5008> event code for avvcbimageX.log

# Suhas

If you found this or any other answer useful please consider the use of the Helpful or Correct buttons to award points.

Don't Backup. Go Forward!