Increase X-large NSX ESG CPU . reaching 100 percent

Hi team ,

NSX Version : 6.3.2

Vcenter : 6.0

Esxi 6,0

   We are hosting about 60+ customers in our data-center . All of their NSX ESG are setup as X-large. I am running into issues where for some customers their NSX ESG which is X-large in Size is reaching 100 percent . Since VM's are system Managed ,  I cant increase CPU since option is greyed out .

pastedImage_0.png

How can i increase CPU of NSX ESG VM's ?  Please help me out if anyone has workaround .

Reply
0 Kudos
3 Replies
T180985
Expert
Expert

Check this: https://patriciocerda.com/nsx-change-cpu-memory-reservations-nsx-edges/

Please mark helpful or correct if my answer resolved your issue. How to post effectively on VMTN https://communities.vmware.com/people/daphnissov/blog/2018/12/05/how-to-ask-for-help-on-tech-forums
Reply
0 Kudos
TarunGuptaAccen
Enthusiast
Enthusiast

Hello T180985,

   I already checked that article . That article is NSX 6.2.3 .. We are running NSX 6.3.2 where we dont get " reservation any more ". Please see screenshot .There is no option of "resource reservation " or any way to define CPU .

pastedImage_3.png

Please help me out .

Reply
0 Kudos
ZibiM
Enthusiast
Enthusiast

Hi Tarun

Try to identify what is causing such CPU usage.

I had once similar situation when edge got hit by 100% cpu usage out of nowhere and it was caused by overload of the incoming network traffic from the internet:

1. There was rate limit on this particular network

2. This particular network got impacted by the ddos

3. Internet routers started to drop about 50% of incoming packets in order to stay within the rate limit

4. NSX Edge started to consume 100% CPU - it was busy trying to maintain TCP sessions, retransmitting dropped packets, and such

Regards