Failed to add vCenter with Skyline

I can't add vCenter Host with skyline corrector.

I confirmed the similar trouble in this community and restarted the corrector or used FQDN of vCenter Host but not successful.

The following message is displayed. Could you please tell me how to deal with the troubles?

The certificate with thumbprint [xxx], provided by your vCenter is not valid due to error: "sun.security.validator.ValidatorException: PKIX path building failed: sun.security.provider.certpath.SunCertPathBuilderException: unable to find valid certification path to requested target"
Press "CONTINUE" if you would like to proceed adding the vCenter with invalid certificate.
  

Couldn't create collection task to test endpoint. -> java.lang.RuntimeException: Couldn't login the client. -> Couldn't login the client. -> Server returned 'request expired' less than 0 seconds after request was issued, but it shouldn't have expired for at least 600 seconds.  

It would be very helpful if you could suggest a solution.

Reply
0 Kudos
1 Solution

Accepted Solutions
Yuva_1990
Hot Shot
Hot Shot
Jump to solution

Hi Tomo,

I have sent you an E-mail,please reply back to it with you availability to work on this issue

Regards

Yuvaraj

View solution in original post

Reply
0 Kudos
4 Replies
Yuva_1990
Hot Shot
Hot Shot
Jump to solution

Hello,

Welcome to Skyline Community.

I understand you have issues adding Vcenter server to skyline and you have tried few troubleshooting steps.We will need to validate the certificates and setup, please provide your contact details on the following URL

VMware Skyline Community - Smartsheet.com

Regards

Yuvaraj

Skyline Support Moderator

Reply
0 Kudos
abetomo
Contributor
Contributor
Jump to solution

Hello Yuvaraj,

Thank your for your cooperation. I registered my information.

Regards

toma

Reply
0 Kudos
Yuva_1990
Hot Shot
Hot Shot
Jump to solution

Hi Tomo,

I have sent you an E-mail,please reply back to it with you availability to work on this issue

Regards

Yuvaraj

Reply
0 Kudos
abetomo
Contributor
Contributor
Jump to solution

Hello Yuvaraj,

As you mentioned, I understood VCSA and Skyline corrector should have the same time strictly.

Thank your for your time and thoughtful support.